ANALYSIS OF TECHNICAL RETROFIT FOR TURBINE NO7 IN GUODIAN JIANBI POWER PLANT[J]. Thermal power generation, 2006, (11): 45-46. DOI: 10.19666/j.rlfd.2006.11.015.
国电谏壁发电厂7号汽轮机技术改造分析
摘要
国电谏壁发电厂于1999年与英国帕森斯公司合作
对7号汽轮机高低压缸通流部分进行了改造
取得了较好的效果。2004年又对7号机中压缸通流部分及凝汽器、真空抽气系统进行了改造
机组的安全性及经济性均有了进一步提高。
Abstract
The flow passage of high-and low-pressure cylinders of turbine no.7 in Guodin Jianbi Power Plant had been retrofitted in 1999 with cooperation of PASONCE company in England
and better result being obtained.The flow passage of intermediate-pressure cylinder
as well as the condenser and the vacuum extraction system had also been retrofitted in 2004