HUANG Sheng. AN APPROACH TO CENTRALIZED-MONITORING OF POWER PLANTS[J]. Thermal power generation, 2004, (8): 4-6. DOI: 10.19666/j.rlfd.2004.08.002.
新建电厂辅助系统集中监控方案探讨
摘要
介绍一种实现火电厂全厂辅助系统集中监控的设想 :根据电厂各辅助系统的特点
将其合理地划分为化水、输煤和除灰 3个子系统
并提出了一种实现该设想的PLC网络结构方案及其应注意的几个问题。
Abstract
A tentative idea for realizing contralized monitoring the whole auxiliary systems in a thermal power plant has been presented. Based on the feature of each auxiliary system
the whole auxiliary systems have been divided into three sub-systems
namely chemical water treatment
coal handling
and ash disposal
a PLC network structural scheme for realizing the said tentative idea being put forward
and several problems needing to pay attention for realizing the said scheme being discussed.