CAUSE ANALYSIS OF EXCEEDING LIMIT FOR POSITIVE DIFFERENTIAL EXPANSION OF INTERMEDIATE PRESSURE CYLINDER ON STEAM TURBINES AND IMPROVEMENT MEASURES THEREOF
LI Shuming et. CAUSE ANALYSIS OF EXCEEDING LIMIT FOR POSITIVE DIFFERENTIAL EXPANSION OF INTERMEDIATE PRESSURE CYLINDER ON STEAM TURBINES AND IMPROVEMENT MEASURES THEREOF[J]. Thermal power generation, 2004, (4): 48-49.
LI Shuming et. CAUSE ANALYSIS OF EXCEEDING LIMIT FOR POSITIVE DIFFERENTIAL EXPANSION OF INTERMEDIATE PRESSURE CYLINDER ON STEAM TURBINES AND IMPROVEMENT MEASURES THEREOF[J]. Thermal power generation, 2004, (4): 48-49. DOI: 10.19666/j.rlfd.2004.04.014.
汽轮机中压缸正胀差超限的原因分析及改进措施
摘要
对黄埔发电厂 2台 30 0MW汽轮机中压缸在机组起动过程中长期出现正胀差超限问题进行了分析
认为中压缸本身结构不完善和蒸汽加热系统中加热蒸汽量不足
以及起动各阶段运行调整不够合理是主要原因。对此
提出了降低汽轮机中压缸正胀差的措施
实施后效果显著。
Abstract
The positive differential expansion exceeding limit for intermediate pressure cylinder often occurred on two 300MW steam turbines in Huangpu Power Plant has been analysed
it is considered that the main causes are as follows:(1) the structure of intermediate pressure cylinder proper isn't perfect; (2) insufficient heating steam flow in the steam heating system; (3) the operation adjustment in every stage of starting up isn't reasonable. For these
measures of decreasing the said positive differential expansion have been taken
and having obvious effectiveness after implementation of abovementioned measures.