RETROFITTING OF HEADER HAND-HOLES FOR A 130 t/h BOILER IN HUATING POWER PLANT[J]. Thermal power generation, 2004, (3): 64-65. DOI: 10.19666/j.rlfd.2004.03.021.
华亭电厂130t/h锅炉联箱手孔改造
摘要
针对华亭电厂 2 5MW机组锅炉联箱手孔在运行中经常泄漏及检修质量难以保证问题
对联箱手孔进行了改造
即将原有手孔盖去掉
在联箱端面上焊接d133mm× 13mm的 2 0G短管
采用球形封头。同时
为了解决盲管和端盖之间角焊缝积水造成该处的应力腐蚀破坏
将盲管向上移动
使内壁和手孔下边缘平齐
封头和盲管之间采用V型坡口焊接。改造后效果很好
彻底解决了手孔泄露问题。
Abstract
Directing against problems of frequent leakages occurred in operation and the repair quality of header handholes being difficult to ensure on the boier of a 25 MW unit in Huating Power Plant
the header handholes have been retrofitted
removing the caps of original handholes of the header
and welding d133mm×13mm short tube of 20G type on end face of the header
and spherical sealing heads being used. Meanwhile
in order to resolve the problem of stress corrosion rupture between the blank pipe and the end cover resulting from accumulated water
the blank pipe has been shifted upward
making the inner wall to be aligned with the lower side edge of handholes
Vshaped bevel welding is used between the sealing head and the blank pipe. After retrofitling
the effectiveness is excellent
having thoroughly solved the leakage problem of handholes.