ANALYSIS OF RELIABILITY-ENHANCING IN START-UP COMMISSIONING OF A COMPLETE HOME-MADE 125MW TURBO-GENERATOR SET[J]. Thermal power generation, 2003, (7): 7-9.
ANALYSIS OF RELIABILITY-ENHANCING IN START-UP COMMISSIONING OF A COMPLETE HOME-MADE 125MW TURBO-GENERATOR SET[J]. Thermal power generation, 2003, (7): 7-9. DOI: 10.19666/j.rlfd.2003.07.002.
the causes of faults and statistic data in start-up commissioning of a complete 125MW unit in one power plant have been analysed. It has been pointed out that the reliability of unit NO.1 enhanced obviously during the time of start-up commissioning because of successively appeared problems having been solved one after another. But the reliability index in narrow sense without considering maintenance of units still remains at a low level until hand-over to trial production. The point estimation of a reliability-enhancing AMSAA model is given
and some forcast analyses having been carried out by using the said model. The results of analyses show