LIU Xin, SHEN Yu-peng, LIU Zhi-jian, et al. Model test on the influence of groundwater seepage velocity on formation of frozen wall in subway cross passage[J]. 2023, 44(9): 2667-2678.
LIU Xin, SHEN Yu-peng, LIU Zhi-jian, et al. Model test on the influence of groundwater seepage velocity on formation of frozen wall in subway cross passage[J]. 2023, 44(9): 2667-2678.DOI: 10.16285/j.rsm.2022.1670.
Artificial ground freezing technology has the advantages of reliable water sealing
low environmental impact and strong applicability. It is one of the effective methods for underground excavation in urban subway to achieve the waterless construction. The cooling power is continuously depleted by groundwater flow
resulting in the delay of closure of frozen wall and the thickness less than expected. A physical model test with groundwater seepage velocities of 0
5
10 and 15 m/d was conducted based on the freezing project of a subway cross passage in Beijing Subway Line. The influence of groundwater seepage velocities on the formation of frozen wall was investigated
and the variation of cooling power in the freezing process was discussed. The results show that under seepage condition
the bottom and top plates of the cross passage intersect first
followed by the downstream sidewall
and finally the upstream sidewall
which is the weak part. At the groundwater seepage velocities of 0
5 and 10 m/d
the closure times of the frozen wall are 60
114 and 444 minites
respectively
while it is impossible to form continuous frozen bodies at 15 m/d. The cooling power increases with the groundwater seepage velocities. The energy consumption at the groundwater seepage velocities of 5
10 and 15 m/d increases by 67.0%
88.5% and 120.1%
respectively compared with no-seepage condition. The results can provide a basis for the design and construction of cross passage freezing under seepage conditions.