ZHANG Yi-ping1, YU Ya-nan1, ZHOU Hong-wei2. Study on causes of post-construction settlement of DJM pile composite foundation at bridge approaches[J]. 2006, (7): 1171-1175.
ZHANG Yi-ping1, YU Ya-nan1, ZHOU Hong-wei2. Study on causes of post-construction settlement of DJM pile composite foundation at bridge approaches[J]. 2006, (7): 1171-1175.DOI: 10.16285/j.rsm.2006.07.031.
In order to study the causes of post-construction settlement of deep-jet-mixed(DJM) pile composite foundation at bridge approaches
the settlement is analyzed and back-analyzed by Biot’s consolidation FEM.The soil constitutive model is the Duncan-Chang nonlinear elastic model in finite element analysis;and Duncan-Chang nonlinear elastic model and Merchant viscoelastic model are used in finite element back-analysis.The computation results show that the traffic load and soil creep are the main causes induced the post-construction settlement of DJM pile composite foundation.The traffic load is the main cause at early period