[1]何成武,徐健余,束家伟,裘井民.新钢8号高炉炉凉处理的探讨[J].能源研究与管理,2017(02):99-101+117.
何成武, 徐健余, 束家伟, et al. Explore of No.8 Blast Furnace Cooling Treatment of Xinyu Iron and Steel Group Co.,Ltd.[J]. 2017, (2): 99-101+117.
[1]何成武,徐健余,束家伟,裘井民.新钢8号高炉炉凉处理的探讨[J].能源研究与管理,2017(02):99-101+117. DOI: 10.16056/j.1005-7676.2017.02.024.
何成武, 徐健余, 束家伟, et al. Explore of No.8 Blast Furnace Cooling Treatment of Xinyu Iron and Steel Group Co.,Ltd.[J]. 2017, (2): 99-101+117. DOI: 10.16056/j.1005-7676.2017.02.024.
对新钢8号高炉炉凉处理进行总结
认为产生炉凉的原因是原燃料质量变差;炉况出现滑尺、塌料、管道行程;炉墙渣皮脱落;炉外渣铁不能及时排出以及工长对渣铁物理热不够重视而操作失误等等。后经减轻焦炭负荷、加大量净焦、降低炉渣碱度、休风堵风口等措施炉况逐渐正常。
The No.8 blast furnace cooling of Xinyu Iron and Steel Group Co.
Ltd. is summarized. The furnace cold due to poor fuel quality
furnace are slide
collapse and exhausted
furnace slag to peel off the walls
slag outside the furnace cannot be discharged and foreman enough attention to slag physical heat
operation errors
and so on. After reducing the load of coke
plus a lot of net coke
reduce the basicity of slag
furnace conditions gradually wind-blocking air inlet moratorium
and furnace conditions gradually back to normal.