吕良. Summary Analysis on Key Work Before the Placement of NI CVTH of AP1000 Nuclear Power Project[J]. 2015, (3): 60-63. DOI: 10.16056/j.1005-7676.2015.03.017.
AP1000核电项目核岛安全壳顶封头就位前关键工作总结分析
摘要
以AP1000三代核电项目为研究对象
收集了国内某沿海AP1000依托项目核岛安全壳顶封头就位前关键工作的完成时间
总结分析了有关制约因素及采取的应对措施
对集团内后续AP1000新项目有一定的经验反馈。
Abstract
This research studies the finish time of key jobs before the placement of NI CVTH of one of the AP1000 3rd generation nuclear power reliance supporting projects
and summarizes and analyzes the constrains and countermeasures. The study tries to provide experience feedbacks to AP1000 projects of the corporation to be built in the future.