1. 国网江西省电力有限公司经济技术研究院,江西,南昌,330096
2. 江西腾达电力设计院有限公司,江西,南昌,330096
3. 国网江西省电力有限公司电力科学研究院,江西,南昌,330096
邵尤国(1994),男,硕士,工程师,从事大电源、新能源和储能电站等接入系统设计工作,E-mail:1447764762@qq.com
周仕豪(1993),男,硕士,工程师,从事直流控制保护及测量相关研究工作,E-mail:1914093166@qq.com
胡晟(1992),男,硕士,高级工程师,从事电网规划与评审工作,E-mail:593082726@qq.com
罗路平(1984),男,硕士,高级工程师,从事大电源、新能源和储能电站等接入系统设计工作,E-mail:55101675@qq.com
聂义民(1994),男,硕士,工程师,从事大电源、新能源和储能电站等接入系统设计工作,E-mail:2806245706@qq.com
刘鸿熹(1990),男,硕士,高级工程师,从事输变电工程、新能源送出线路设计工作,E-mail:835075769@qq.com
魏志伟(2001),男,硕士,助理工程师,从事主网潮流分析、电能质量研究工作,E-mail:1328393736@qq.com
纸质出版:2026
移动端阅览
邵尤国, 周仕豪, 胡晟, 罗路平, 聂义民, 刘鸿熹, 魏志伟. 风电富集地区独立储能电站接入电网电压等级实例分析[J]. 农村电气化, 2026, (7): 39-43.
Shao Youguo, Zhou Shihao, Hu Sheng, et al. Case Study on the Grid Integration Voltage Level of an Independent Energy Storage Station in a Wind Rich Region[J]. Rural Electrification, 2026, (7): 39-43.
邵尤国, 周仕豪, 胡晟, 罗路平, 聂义民, 刘鸿熹, 魏志伟. 风电富集地区独立储能电站接入电网电压等级实例分析[J]. 农村电气化, 2026, (7): 39-43. DOI: 10.13882/j.cnki.ncdqh.2604A017.
Shao Youguo, Zhou Shihao, Hu Sheng, et al. Case Study on the Grid Integration Voltage Level of an Independent Energy Storage Station in a Wind Rich Region[J]. Rural Electrification, 2026, (7): 39-43. DOI: 10.13882/j.cnki.ncdqh.2604A017.
目前,独立储能电站已进入快速发展阶段,其在接入电网过程中面临着复杂多样的场景。文章分析了一项风电富集地区独立储能电站接入电网电压等级实例,针对风电富集、负荷规模较小的某县电网,系统性考虑区域源-网-荷-储实际情况,基于电力平衡分析和峰谷分时电价运行分析,利用储能电站全年充放电次数和电网
N
− 1故障下主变负载率指标,从安全性、经济性和系统发展角度综合分析了一项100 MW功率的独立储能电站接入电网电压等级问题,可为类似案例的储能电站接入系统设计提供借鉴。
Independent energy storage stations are in a stage of rapid development and face complex and diverse scenarios when connected to the power grid. This paper analyzes a case of the grid integration voltage level of an independent energy storage station in a wind rich region. Focusing on a county power grid characterized by abundant wind power and a relatively small load scale
the study systematically considers the actual conditions of regional source
grid
load
and energy storage. Based on power balance analysis and operation analysis under peak valley time of use electricity prices
and using indicators such as the annual number of charging and discharging cycles of the energy storage station and the main transformer loadi
ng rate under
N
− 1 contingencies
the grid integration voltage level of a 100 MW independent energy storage station is comprehensively analyzed from the perspectives of safety
economy
and power system development. This analysis can provide a reference for the grid integration system design of energy storage stations in similar cases.
韩晓宇,李栩萌,周晓航.中国风光发电高质量发展展望[J].中国国情国力,2026(2):8-13.
Bian N,Kawasaki S.Two Stage Stochastic Optimization Scheduling of Power System Considering Thermal Power Units and Energy Storage Peak Shaving Pricing Strategies[J].Journal of Electrical Engineering Technology,2025,20(5):2961-2975.
孟凡雷.贺州抽水蓄能电站工程库址选择[J].广西水利水电,2024(4):68-72,76.
贾一凡,安海舰,周敏刚,等.电化学储能电站研究现状综述[J].电力电容器与无功补偿,2025,46(3):99-105.
杜昊易,李尧,陈换军,等.电化学储能技术及应用案例综述[J].广东化工,2023,50(22):50-52.
何卓怡,余音.电池储能在电网负荷调节及新能源消纳中的应用[J].农村电气化,2022(12):83-84,90.
吴双.水电与储能系统联合优化调度研究[J].农村电气化,2025(11):64-67.
DL/T 5810—2020 电化学储能电站接入电网设计规范[S].
罗九根.广东清远独立储能电站布点及接入系统研究[J].自动化应用,2025,66(3):159-161,166.
赵琦,管霖,吕耀棠,等.储能电站在含光伏电源配电网中的优化配置[J].广东电力,2018,31(7):1-7.
肖利坤.山东省分时电价对光伏和储能系统的影响[J].农村电气化,2023(8):65-67.
GB/T 1094.7—2024 电力变压器 第7部分:油浸式电力变压器负载导则[S].
0
浏览量
0
下载量
0
CSCD
关联资源
相关文章
相关作者
相关机构
京公网安备11010802024621