Staged fracturing technology with full bore infinite sliding sleeve of casing-damaged horizontal wells for deep shale gas: A case study of Well-WY9-2HF
LONG Gang, XUE Lina, YANG Xiaoli. Staged fracturing technology with full bore infinite sliding sleeve of casing-damaged horizontal wells for deep shale gas: A case study of Well-WY9-2HF[J]. Petroleum Reservoir Evaluation and Development, 2021, (2): 85-88+100.
LONG Gang, XUE Lina, YANG Xiaoli. Staged fracturing technology with full bore infinite sliding sleeve of casing-damaged horizontal wells for deep shale gas: A case study of Well-WY9-2HF[J]. Petroleum Reservoir Evaluation and Development, 2021, (2): 85-88+100. DOI: 10.13809/j.cnki.cn32-1825/te.2021.02.011.
The casing damage of horizontal "wells for shale gas
especially for deep shale gas
has always been a problem that troubles the staged fracturing development of shale gas.The conventional methods
such as casing patching and chemical plugging
cannot simultaneously meet the demands of high pressure
high flow rate and small bridge plug passing during fracturing
resulting in the difficult implementation of the staged fracturing technology through pumping of bridge plugs.Besides
the staged fracturing technology
with multi-packer is difficult to meet the requirements of pumping rate and scale due to the limited number of segments and limited displacement
resulting from the limited range of the ball-drop sliding sleeve.Taking Well-WY9-2 HF as an example
by conducting the researches such as risk demonstration
pipe string mechanical analysis and structural optimization
tool development and improvement
and wellbore simulation test
the following conclusions are drawn:the string with suspension packer is suitable for isolating the casing-damaged sections;the combination of the upper casing and the lower tubing for injection can raise the pump rate;the full bore infinite sliding sleeve can increase the number of segments and the pump rate;together with multi-packer
well control safety measures and high-rate segmented fracturing technique
the full bore infinite sliding sleeve is used to realize a large-scale and high-rate fracturing with 31 stages in Well-WY9-2HF
which achieves the expected targets and obtains a commissioning production of 8.75×10
4
m
3
/d.This technology can be used as a reference for the fracturing and commissioning of such wells.