In order to investigate the effects of different working conditions and key parameters on the stress
deformation and displacement of frame-shear structure underground substation
based on the actual underground substation project
an in-depth study is carried out by using the finite element analysis software SAP2000.The results show that the floor de-sign of underground substation is determined by anti-floating under construction conditions
the external wall design is determined by groundwater level under operating conditions
the internal component design is determined by equipment load and groundwater level under operating conditions
and the seismic conditions have no con-trolling effect on component design;with or without earthquake action and seismic fortification intensity
the lateral displacement of external wall and axial force of beam in underground substation are significantly affected
and the displacement and bending moment of raft foundation are affected to a certain extent
but the influence on bending moment of external wall
shear force and bending moment of beam and internal force of frame column is not obvious;with the increase of groundwater level
except that the downward displacement of raft foundation de-creases gradually
the internal force and deformation of raft foundation
exterior wall
beam and other main members all increase in varying degrees;with the increase of the thickness of the external wall
the lateral de-formation of the external wall decreases
the bending moment increases
and the downward displacement of the raft foundation increases;with the increase of the thickness of the raft foundation
the downward displacement of the raft foundation decreases
the bending moment increases
and the lateral deformation of the external wall decreases slightly.