引进型300MW机组阀切换试验及运行经济性分析
摘要
简要介绍了引进型 30 0 MW汽轮机组阀切换的过程
通过 4个负荷下单阀和顺序阀运行的热力特性试验
综合分析了机组单阀、顺序阀运行的热经济性
为机组各种负荷下运行方式的经济调度提供依据。
Abstract
In this paper the valve switching process of an imported 300MW generation unit is introduced. Based on the analysis of thermodynamic performance tests under single and sequence valve operations subjected to 4 different load levels
the thermal economic coefficients are presented. The coefficients lay the foundation of economic dispatch of the generator under various load levels.