difficult supporting and other problems in the construction of deep and long tunnels
the superiority and disadvantage of tunnel construction method are conducted
such as drill-blasting method
TBM method
and TBM bored pilot+enlarging method. TBM bored pilot+enlarging method provides a new idea for tunnelling design of deep and long tunnels. Due to the remarkable differences in geological condition between deep tunnels and shallow tunnels
there are three crucial problems for TBM construction
namely
rockburst
TBM jamming (large deformation)
and construction accidents (water gush
mud burst
etc.) attributed to inaccurate geological prediction. In order to detect the occurrence of TBM jamming
theoretical analysis and numerical simulation of TBM construction are conducted in deep soft rock and hard rock under certain geological conditions. The results show that the jamming occurs in deep soft rock