Simplified calculation method of horizontal displacements for the composite retaining system of cement-soil piles and soil nailing
岩土力学2007年28卷第9期
作者机构:
1. 同济大学 地下建筑与工程系,上海,200092
2. 郑州大学 土木工程学院,郑州,450002
作者简介:
基金信息:
DOI:
中图分类号:TU472
网络首发:2013-10-15,
纸质出版:2007
稿件说明:
移动端阅览
秦会来, 郭院成. 水泥土桩复合土钉水平位移简化计算[J]. 岩土力学, 2007,28(9).
QIN Hui-lai, GUO Yuan-cheng. Simplified calculation method of horizontal displacements for the composite retaining system of cement-soil piles and soil nailing[J]. 2007, 28(9).
QIN Hui-lai, GUO Yuan-cheng. Simplified calculation method of horizontal displacements for the composite retaining system of cement-soil piles and soil nailing[J]. 2007, 28(9).DOI:
the incremental calculation method is applied to the composite retaining system of cement-soil piles and soil nailing(CRSCSPSN). According to the unloading effect of excavation and the forming mechanism of soil-nail forces
the establishment method for the proportional coefficients of soil-nail forces is presented and the method makes it possible to calculate the soil-nail forces by increments. The incremental calculation method can effectively explain the influence of construction on soil-nail forces; and the calculation results of this method are more consistent with those of the measured. According to the deformation compatibility between the cement-soil piles and soil nails
and the relations between force and deformation both for soil nails and cement-soil piles
the simplified deformation calculation method for CRSCSPSN is presented. The deformation calculation method proposed is also based on the incremental theory. At last
there is an engineering case of which the calculated horizontal-displacement results and measured results are compared; and the comparison conclusions show that the simplified calculation method of horizontal displacements for CRSCSPSN is acceptable and effective.