YANG Ping, GAO Longjun, WANG Xiaogang, et al. Optimization of load control strategy for a supercritical 600MW unit boiler[J]. Thermal power generation, 2015, 44(8): 113-115.
YANG Ping, GAO Longjun, WANG Xiaogang, et al. Optimization of load control strategy for a supercritical 600MW unit boiler[J]. Thermal power generation, 2015, 44(8): 113-115.DOI:
超临界600MW机组锅炉负荷控制策略优化
摘要
针对某超临界600 MW机组锅炉煤质变化、磨煤机一次风量测量不准确
使得锅炉负荷难以自动控制的问题
在分析给煤量跟踪给水流量和给水流量跟踪给煤量2种锅炉负荷控制策略的基础上
采用在控制中增加煤质自校正功能的方法
对给水流量跟踪给煤量锅炉负荷控制策略进行了优化。实际应用结果表明
在自动发电控制(AGC)方式且机组大幅度变负荷工况下
锅炉负荷控制系统能够以1.0~1.5%/min的速率响应AGC指令
并将主蒸汽压力、温度控制在±0.4 MPa和±4℃内
满足DL/T 774—2004标准的要求。
Abstract
In a supercritical 600 MW unit
the coal quality changes and the primary air flow measurement of the coal mill is inaccurate
so the boiler load can not be automatically controlled.Against this problem
two boiler load control strategies were analyzed
the feed coal following the feed water mode and the feed water following the feed coal mode.On this basis
a boiler load control strategy with coal quality automatic calibration function was applied to optimize the feed water and feed fuel system.The results show that
in automatic generation control(AGC)mode with large load variations
the boiler load control system can respond the AGC load demand with speed of 1.0~1.5%/min
and can constrain the main steam pressure and temperature controlling error within ±0.4 MPa and ±4 ℃ respectively
which meets the corresponding target aim in the DL/T 774—2004.