MA Yue Hebei Electric Power Design & Research Institute. Feasibility analysis on equipping no startup boiler for class F combined cycle units[J]. Thermal power generation, 2013, 42(8): 102-106.
MA Yue Hebei Electric Power Design & Research Institute. Feasibility analysis on equipping no startup boiler for class F combined cycle units[J]. Thermal power generation, 2013, 42(8): 102-106.DOI:
More and more class F gas turbine combined cycle unit was constructed in China.Combined with function of startup steam and status of startup boiler in combined cycle units
the feasibility of equipping no startup boilers for class F combined cycle unit was investigated.The results showed that
for the class F combined cycle units with common configuration of single shaft and multiple-shaft
the one with generator middle-set can be operated without the startup boiler
while the one with generator end-set must equip startup boiler.According to the configuration features
the multiple-shaft combined cycle units which consist of the M701Fturbines should set the startup boiler;while that consist of the SGT5-4000Fturbines manufactured by Siemens company and 9Fturbines manufactured by GE company can start without startup boiler.Using the steam generated from waste heat boiler as the startup steam will prolong the unit startup time
increase the fuel consumption and complexity of dispatching with the power grid during unit starting.So it suggested that the combined cycle unit should be equipped with startup boiler.