关志军. ±800kV工程特高压直流输电铁塔真型试验研究[J]. 山西电力, 2022, (4): 19-22.
引用本文: 关志军. ±800kV工程特高压直流输电铁塔真型试验研究[J]. 山西电力, 2022, (4): 19-22.
GUAN Zhi-jun. Full-scale Test Research on ±800 kV UHVDC Transmission Tower[J]. Shanxi Electric Power, 2022, (4): 19-22.
Citation: GUAN Zhi-jun. Full-scale Test Research on ±800 kV UHVDC Transmission Tower[J]. Shanxi Electric Power, 2022, (4): 19-22.

±800kV工程特高压直流输电铁塔真型试验研究

Full-scale Test Research on ±800 kV UHVDC Transmission Tower

  • 摘要: 介绍了白鹤滩—江苏±800 kV特高压直流输电线路工程铁塔真型试验情况,对铁塔首先破坏位置的实际破坏荷载与理论破坏荷载进行了分析对比,建议输电线路铁塔在经验不足时按照b类截面选取稳定系数。

     

    Abstract: Based on a detailed introduction of the full-scale test of the transmission tower of Baihetan-Jiangsu ± 800 kV UHVDC transmission line project,the actual failure load and theoretical failure load at the first failure position of the tower are analyzed and compared.It is suggested that the stability coefficient of the transmission line tower should be selected according to the type b section when the experience is insufficient.

     

/

返回文章