肖志军, 张亮亮, 曹波, 罗彦. 超长距离顶管顶力估算与中继间设置研究[J]. 内蒙古电力技术, 2023, 41(4): 66-72. DOI: 10.19929/j.cnki.nmgdljs.2023.0057
引用本文: 肖志军, 张亮亮, 曹波, 罗彦. 超长距离顶管顶力估算与中继间设置研究[J]. 内蒙古电力技术, 2023, 41(4): 66-72. DOI: 10.19929/j.cnki.nmgdljs.2023.0057
XIAO Zhijun, ZHANG Liangliang, CAO Bo, LUO Yan. Research on Jacking Force Estimation and Relay Room Setting of Ultra-Long Distance Pipe Jacking[J]. Inner Mongolia Electric Power, 2023, 41(4): 66-72. DOI: 10.19929/j.cnki.nmgdljs.2023.0057
Citation: XIAO Zhijun, ZHANG Liangliang, CAO Bo, LUO Yan. Research on Jacking Force Estimation and Relay Room Setting of Ultra-Long Distance Pipe Jacking[J]. Inner Mongolia Electric Power, 2023, 41(4): 66-72. DOI: 10.19929/j.cnki.nmgdljs.2023.0057

超长距离顶管顶力估算与中继间设置研究

Research on Jacking Force Estimation and Relay Room Setting of Ultra-Long Distance Pipe Jacking

  • 摘要: 对顶力估算及中继间设置在设计施工过程中的关键技术进行研究,分析实测顶力与估算顶力的对比情况、中继间设置及使用情况。以珠海某220 kV电缆线路穿越马骝洲水道顶管工程为例,该超长距离顶管单次顶进1022 m,使用2.2 m内径的钢筋混凝土管,穿越地层有黏土、淤泥质土、粗砂等。先按规范进行顶力估算及中继间设置,工程实施过程中实测顶力变化情况,获得估算顶力与实测顶力的对比曲线,反算出实测平均摩阻力的变化曲线。理论分析与工程监测结果对比表明:正常顶进条件下,全程平均摩阻力可以降低到1.5 kPa左右,但在停止顶进48 h后再次启动时,全程平均摩阻力急剧增加到4.1 kPa,实测总顶力接近估算顶力值,表明应用触变泥浆减阻、连续顶进时管浆管土部分接触是超长距离顶管的理想状态。综合分析认为,顶力控制是超长距离顶管成功的关键,并提出按地层分段进行平均摩阻力取值的建议,同时提出中继间配置方案。

     

    Abstract: This paper explores the critical technologies in the design and construction process of the jacking force estimation and relay room setting. The comparison between the measured and estimated jacking force, and the setting and use of relay room are also studied. Based on the pipe jacking project of a 220 kV cable line project crossing the Monkey Island waterway in Zhuhai, the ultra-long distance pipe jacking project involves a single jacking of 1022 m, and uses reinforced concrete pipes with an inner diameter of 2.2 m. The crossing stratum includes clay, mucky soil, coarse sand, etc. Firstly, the jacking force is estimated and the relay room is set according to the specifications. Then, during the implementation of the project, the variation of the jacking force is measured. Finally, the comparison curve between the estimated jacking force and the measured jacking force is obtained. The variation curve of the measured average friction is inversely calculated. The comparative analysis between theoretical calculation and measured results shows that under normal jacking conditions, the average frictional resistance in the whole process can be reduced to about 1.5 kPa. However, after the jacking has been stopped for 48 hours, when starting again, the average frictional resistance in the whole process increased sharply to the level of 4.1 kPa. The measured total jacking force is close to the estimated jacking force value, indicating that using thixotropic mud to reduce resistance and continuous jacking is an ideal state for ultra-long distance pipe jacking. This paper proposes that jacking force control is the key to the success of ultra-long distance pipe jacking, and it is suggested to take the average frictrional resistance value according to the stratum section, and the configuration scheme of relay room is proposed.

     

/

返回文章
返回