刘金生,张磊,赵振杰.配电网网格可靠性目标制定方法研究[J].南方能源建设,2022,09(01):109-114.. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.016
引用本文: 刘金生,张磊,赵振杰.配电网网格可靠性目标制定方法研究[J].南方能源建设,2022,09(01):109-114.. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.016
LIU Jinsheng,ZHANG Lei,ZHAO Zhenjie.Research on the Methods of Gridding Reliability Object Setting for Distribution Network[J].Southern Energy Construction,2022,09(01):109-114.. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.016
Citation: LIU Jinsheng,ZHANG Lei,ZHAO Zhenjie.Research on the Methods of Gridding Reliability Object Setting for Distribution Network[J].Southern Energy Construction,2022,09(01):109-114.. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.016

配电网网格可靠性目标制定方法研究

Research on the Methods of Gridding Reliability Object Setting for Distribution Network

  • 摘要:
      目的  供电网格具有可靠性管理、线损管理和运行维护方便等优势,已被越来越多的电网企业采纳。目前,电网企业只制定了总体可靠性目标,没有制定电网网格的可靠性目标,网格的建设标准仍然采用供电分区建设标准。这对于发展差异较大的城市来说,存在部分网格的供电可靠性需求较高,但规划建设标准却较低的现象。
      方法  通过数理统计方法找出政治、经济、负荷等因素对供电网格的影响,形成定量的结果,再通过聚类分析,划分出不同的供电网格类别。然后统计网格历史年停电时户数,考虑计划停电时间占比趋势,利用层次分析法找出不同类供电网格平均停电时间与总平均停电时间的关系,将规划区域可靠性目标合理地分配到供电网格。
      结果  该方法使得网格的供电可靠性目标与实际建设需求相适应,便于网格内配电网地精益规划和建设。
      结论  通过算例证明,该方法能够合理规划配电网网格可靠性目标,对配电网建设标准选择具有较强地指导意义。

     

    Abstract:
      Introduction  The gridding has been adopted by more and more power grid enterprises as its good performance in reliability management, line loss management and operating maintenance. At present, the power grid enterprises only set overall reliability targets instead of gridding reliability objectives, and the gridding still adopts standards of construction of power supply zones, which leads to high demands in power supply reliability but low planning and construction standard in cities with large differences in development.
      Method  The influence of political, economic, load and other factors on power grid was found through mathematical statistics, and quantitative results were formed. Then, different gridding categories were divided with cluster analysis. Considering the historical outage household numbers and proportion of planned outages, the relations between average outage time and total outage time in different types of power grids were sort out with analytic hierarchy process (AHP), and the reliability target of the planning area was reasonably allocated to the gridding.
      Result  The method meets the requirments of reliability objectives and actual demands in grid power supply construction, which is convenient for lean planning and construction of power network in gridding.
      Conclusion  The examples in this paper show that the method has strong guiding significance forreliability targets and distribution network construction.

     

/