In response to a series of issues encountered during the preliminary land clearance and compensation work for the Inner Mongolia power grid construction
including mismatches between project planning and territorial spatial planning
unclear boundaries of authority and responsibility for cross-regional construction
inconsistent land acquisition compensation standards across regions
last-minute planting and construction by local residents prior to construction
information asymmetry between government and enterprises
and a lack of oversight for civilized construction practices
which have resulted in significant coordination challenges and delays in construction progress
drawing on extensive field experience in power transmission and transformation projects
this paper proposes the following measures of prioritizing planning compliance
establishing a collaborative responsibility mechanism between government and enterprises
issuing advance public notices and retaining visual documentation
conducting on-site surveys to assess land features and local conditions
addressing civil disputes through categorized and tiered mediation
optimizing tower site and route plans
standardizing compensation criteria and streamlining payment procedures
promoting civilized construction practices
and implementing post-project evaluations and dynamic monitoring. After implementing these measures in projects such as the electrified railway from Hohhot to Zhangjiakou and the Huade-Siziwang Banner 220 kV new energy aggregation power supply project
the practice of unauthorized construction is effectively curbed
various land acquisition disputes are properly resolved
and the projects are completed and put into operation on schedule.