Research on flexible peak load regulation strategy and performance of typical coal-fired units
In order to improve the flexibility of coal-fired units
a flexible peaking operation method is proposed by combining the heat storage by extracting the reheated steam and secondary air heating by extracting the main steam. Taking the ultra-supercritical 660 MW indirect air-cooled unit as the object of study
the performance of the unit under different peaking schemes at 30% BMCR operating conditions
the energy reuse rates under different heat release conditions and the performance of the combined load reducing operation mode are analyzed. The results show that the energy reuse rates of extracting main steam heat storage
extracting main steam heating secondary air and extracting hot reheat steam heat storage are 55.13%
84.74% and 46.24%
respectively
at a peak-load shaving capacity of 20 MW with 75% THA heat release condition. Under the premise of ensuring the safety of boiler combustion and heating surface
the combined load reducing operation mode can achieve a peak peak-load shaving capacity of 46 MW
and the energy reuse rate can reach 74% when the heat release condition is 75% THA. This study can provide a reference for flexible peak-load regulation of coal-fired units.
Comprehensive performance analysis of solar hybrid coal-fired power generation
Coupling method and thermal performance analysis for molten salt heat storage tower solar energy power station and thermal power unit
Design and performance comparison of peak shaving system of coal-fired unit aided by molten salt heat storage
Thermodynamic modeling and influence analysis of key parameters of heavy-duty gas turbine considering turbine stage cooling
Thermo-economic evaluation of a solid waste plasma gasification power system integrated with a combined heat and power plant
Related Author
AN Liansuo
XU Mei
ZHANG Heng
CHEN Haiping
FENG Lei
DONG Xuehui
WANG Huijie
ZAN Yongchao
Related Institution
National Thermal Power Engineering Technology Research Center, North China Electric Power University
College of Energy, Power and Mechanical Engineering, North China Electric Power University
Key Laboratory of Heat Transfer Enhancement and Process Energy Conservation, Ministry of Education, and Beijing Key Laboratory of Heat Transfer and Energy Utilization, Beijing University of Technology
Shanghai Power Generation Equipment Complete Design and Research Institute Co., Ltd