Application and optimization of cold-state preheating technology for steam turbine of gas-steam combined cycle unit
During the cold state start-up of gas-steam combined cycle unit
the metal temperature of steam turbine is low
in order to avoid the thermal stress generated during the rotation process affecting the unit safety
the steam turbine needs medium-speed heater to increase the metal temperature
which greatly limits the ability of the unit to quickly respond to peak regulation of the power grid. Therefore
steam turbine preheating system is applied in the gas-steam combined cycle unit for the first time
and the twice cold state start-up processes of the unit before and after the steam turbine preheating system is put into operation are compared. The results show that
the preheating system can make the steam turbine reach the warm state start-up requirements before the whole cold state start-up
which greatly shortens the start-up time of the unit under the cold state start-up and improves the economy of the unit. In addition
through optimization for cold-state preheating process of the unit
the phenomenon of rapid decline of the unit speed caused by insufficient steam source pressure is effectively avoided. This experience can be referred for the relevant combined cycle units.
SIMPLIFIED FINITEELEMENT CALCULATION MODEL OF TEMPERATURE FIELD FOR STEAM TURBINE ROTOR
APPLICATION OF SOLID SELF-LUBRICATING TECHNOLOGY IN POWER PLANTS
STUDY ON CONTROL SYSTEM SETTING OF DOUBLE EXTRACTION ADJUSTABLE STEAM TURBINE
ANALYSIS OF FAULTS OCCURRED IN SYNCHRONIZATION WITH POWER NETWORK FOR TAKING INITIAL LOAD BY STEAM TURBINE OF A 180MW GAS AND STEAM TURBINE COMBINED CYCLE UNIT
CAUSE ANALYSIS AND IMPROVEMENT MEASURES FOR PRESSURE REDUCTION OF LUBRICANT OIL DURING STARTUP OF 300MW UNITS