LI Jun-minDepartment of Hai'yang Nuclear Power Project under Zhongdiantou Electric Power Engineering Co Ltd. ANALYSIS ABOUT FCB FUNCTION OF 350MW UNIT MANUFACTURED BY MITSUBISHI CORPORATION[J]. Thermal power generation, 2009, 38(1): 83-86.
DOI:
LI Jun-minDepartment of Hai'yang Nuclear Power Project under Zhongdiantou Electric Power Engineering Co Ltd. ANALYSIS ABOUT FCB FUNCTION OF 350MW UNIT MANUFACTURED BY MITSUBISHI CORPORATION[J]. Thermal power generation, 2009, 38(1): 83-86. DOI: 10.19666/j.rlfd.2009.01.023.
ANALYSIS ABOUT FCB FUNCTION OF 350MW UNIT MANUFACTURED BY MITSUBISHI CORPORATION
摘要
对日本三菱公司制造的河津电厂350MW机组快速甩负荷(FCB)功能的逻辑设计及存在问题进行分析
探讨了该机组FCB功能的设计思想
为大型机组实现FCB功能的可行性和必要性提供参考。
Abstract
The logic design and existing problems in the fast cut back(FCB)function of 350 MW unit manufactured by Mitsubishi Corporation of Japan
and installed in Hejin Power Plant
have been analysed
and the design ideology of FCB function for 350 MW units manufactured by Mitsubishi Corporation
as well as the feasibility and necessity of realizing FCB function on large-capacity units