CAUSE ANALYSIS OF SCREWED HANGER ROD BREAKAGE ON CONSTANT FORCE HANGING BRACKET FOR MAIN STEAM PIPELINE OF 300 MW UNIT IN ONE POWER PLANT
摘要
介绍了某电厂300 MW机组主蒸汽管恒力吊架螺纹吊杆断裂情况
通过材质、断口分析和断裂力学计算表明
断裂为吊杆受到异常的拉伸+弯曲疲劳载荷作用所致
并与吊杆转轴锈蚀相关。对此
建议对运行时间较长且性能下降的恒力吊架进行全面检查并逐步更换
以确保管道系统安全。
Abstract
The situation of screwed hanger rod breakage on costant force hanging bracket for main steam pipeline of 300 MW unit in one power plant has been presented.Through material quality inspection
fracture analysis
and breakage mechanics calculation
it shows that the quality and norm of said hanger rod are conform to the requirements of standard
the causes leading to breakage of the hanger rod are due to effects of abnormal tension+bending fatigue load
and being related to rotating shaft corrosion of the constant force hanging bracket.For this
it is recommented to conprehensively inspect the constant force hanging bracket
which has longer operation period and lowered performance