QIN Jian-zhu1, CHEN Shun-min2, JIANG Jian-zhong3, et al. CAUSE ANALYSIS ABOUT SLAGGING IN THE START-UP PROCESS OF BOILERS AND PREVENTION THEREOF[J]. Thermal power generation, 2008, (9): 32-34.
DOI:
QIN Jian-zhu1, CHEN Shun-min2, JIANG Jian-zhong3, et al. CAUSE ANALYSIS ABOUT SLAGGING IN THE START-UP PROCESS OF BOILERS AND PREVENTION THEREOF[J]. Thermal power generation, 2008, (9): 32-34. DOI: 10.19666/j.rlfd.2008.09.009.
CAUSE ANALYSIS ABOUT SLAGGING IN THE START-UP PROCESS OF BOILERS AND PREVENTION THEREOF
摘要
龙岩发电有限责任公司4×135MW机组循环流化床(CFB)锅炉在起动过程多次出现结焦现象
分析认为其根本原因在于给煤口给煤不均匀导致床温偏差大
炉内积存大量的未燃焦炭
一、二次风量调整不及时等。对此
提出了对2号炉A、B刮板给煤机的下煤口进行改造
将A2、B2下煤口由原来的600mm×600mm的方形改成底边600mm、高600mm的三角形
以及调整一、二次风量使氧量不低于8%等。改造实施后
经近一年的运行锅炉未再出现过结焦现象。
Abstract
The slagging phenomenon has appeared many times on CFB boilers of 4×135 MW units in Longyan Power Generation Co Ltd during the process of start-up.It is believed from analysis that the basic causes are as follows:uneven coal-feeding throuh coal feed port
leading to large deviation of bed temperature;a lot of unburnt coke accumulated in the furnace;and the regulation of primary air and secondary air isn't in time
etc..For these
retrofit measure of coal-dropping port for the scraper type coal feeders A and B equiped for boiler no.2 has been put forward
the coal-dropping ports A2 and B2 being reshaped from the original square of 600 mm ×600 mm to a triangle with bottom side of 600 mm and a height of 600 mm;at the same time
the primary air and secondary air have been adjusted in time
making the oxygen content to be not lower than 8%.After implementation of retrofit
the slagging phenomenon hasn't appeared again in the process of operation about one year.