CAUSE ANALYSIS OF BARREL SHELL LEAKAGE FOR HIGH-PRESSURE HEATER NO.3 OF 600 MW UNIT IN ONE DOWER PLANT
更新时间:2025-09-28
    • CAUSE ANALYSIS OF BARREL SHELL LEAKAGE FOR HIGH-PRESSURE HEATER NO.3 OF 600 MW UNIT IN ONE DOWER PLANT

    • Thermal Power Generation   Issue 2, Pages: 52-55(2008)
    • DOI:10.19666/j.rlfd.2008.02.011    

      CLC: TM621
    • Published:2008

    移动端阅览

  • CHEN Bing-bing1, LOU Yu-min3, ZHOU Jiang2, et al. CAUSE ANALYSIS OF BARREL SHELL LEAKAGE FOR HIGH-PRESSURE HEATER NO.3 OF 600 MW UNIT IN ONE DOWER PLANT[J]. Thermal power generation, 2008, (2): 52-55. DOI: 10.19666/j.rlfd.2008.02.011.

  •  
  •  

0

Views

114

下载量

1

CSCD

Alert me when the article has been cited
提交
Tools
Download
Export Citation
Share
Add to favorites
Add to my album

Related Articles

ANALYSIS OF “UNSYMMETRIC BURNING” PROBLEM IN A W-SHAPED FLAME BOILER OF 600 MW UNIT
CAUSE ANALYSIS OF SOMEWHAT LOW RATE FOR PUTTING HIGH-PRESSURE HEATER OF 200 MW UNITS INTO SERVICE AND RETROFITTING MEASURES THEREOF
CONTROL STRATEGY OF SUPERCRITICAL ONCE-THROUGH BOILER FOR 600 MW UNITS
CAUSE ANALYSIS OF HIGH-PRESSURE HEATER LEAKAGE FOR 300MW UNIT AND COUNTERMEASURES THEREOF
CAUSE ANALYSIS OF JAMMING AND AIR LEAKAGE OF THE HOT-AIR DAMPER AND RETROFIT THEREOF

Related Author

MIAO Changxin
WANG Jianwei
HE Dongrong
HUANG Hongyan
CHEN Huadong
CAO Zhi-yang(Huaneng Pinliang Power Generation Co Ltd
AN Xue-zhong
XIE Wen-jun

Related Institution

Shandong Electric Power Research Institute
Liaocheng Power Plant
Shaoguan Power Plant
Zhejiang Electric Power Education and Training Center
Zhejiang Electric Power Design Institute
0