STUDY ON CALCULATION METHOD FOR TARGET VALUE OF BOILER OPERATION OPTIMIZATION IN THERMAL POWER PLANTS[J]. Thermal power generation, 2006, (9): 27-29.
DOI:
STUDY ON CALCULATION METHOD FOR TARGET VALUE OF BOILER OPERATION OPTIMIZATION IN THERMAL POWER PLANTS[J]. Thermal power generation, 2006, (9): 27-29. DOI: 10.19666/j.rlfd.2006.09.009.
STUDY ON CALCULATION METHOD FOR TARGET VALUE OF BOILER OPERATION OPTIMIZATION IN THERMAL POWER PLANTS
摘要
通过分析锅炉运行目标值的影响因素
指出运行目标值可分为直接运行参数和间接性能参数两类;提出了间接性能参数目标值的计算方法
并通过某电厂600MW机组运行优化管理系统的实际应用
给出了直接运行和间接性能两类参数的耗差计算方法。应用结果表明
两类参数对煤耗的影响量一致
可用于锅炉性能监测和诊断。
Abstract
Through analysis of affecting factors for the target value of boiler operation optimization
it has been pointed out that the target value of operation optimization can be classified into two kinds
namely direct operation parameters and indirect performance parameters. The calculation method of target value for indirect performance parameters has been put forward
and through practical application of the operation optimization management system for 600 MW unit in one power plant
the calculation method of consumption difference between two kinds of parameters
i.e. direct operation parameters and indirect performance parameters
having been given. Results of application show that the influence of two kind parameters upon the coal consumption is identical
it can be used for supervisory and diagnosis of the boiler performance.