DESIGN,ERRECTION,AND COMMISION DEBUGGING OF 600MW DIRECT AIR-COOLED UNIT PROJECT IN GUODIAN DATONG POWER-GENERATION CO LTD
更新时间:2025-09-28
    • DESIGN,ERRECTION,AND COMMISION DEBUGGING OF 600MW DIRECT AIR-COOLED UNIT PROJECT IN GUODIAN DATONG POWER-GENERATION CO LTD

    • Thermal Power Generation   Issue 6, Pages: 29-31(2006)
    • DOI:10.19666/j.rlfd.2006.06.009    

      CLC: TM621.3
    • Published:2006

    移动端阅览

  • WU Quan. DESIGN,ERRECTION,AND COMMISION DEBUGGING OF 600MW DIRECT AIR-COOLED UNIT PROJECT IN GUODIAN DATONG POWER-GENERATION CO LTD[J]. Thermal power generation, 2006, (6): 29-31. DOI: 10.19666/j.rlfd.2006.06.009.

  •  
  •  

0

Views

162

下载量

4

CSCD

Alert me when the article has been cited
提交
Tools
Download
Export Citation
Share
Add to favorites
Add to my album

Related Articles

ACC ACCEPTANCE TEST AND ITS ANALYSIS ON A 600 MW UNIT
Research of neighbor inter-connection on cold end system of thermal power units
Key points of SNCR denitrification technology for coal fired boilers
Comparative analysis on control algorithm for direct air cooling system of coal fired power plant
Effect of heightening windbreak on flow field of a direct air coolling system

Related Author

YANG Hai-sheng1
ZHOU Lan-xin1
LIU Chun-bao2
SHANG Zhong-hua2
LIU Hong-xia1.North China Electric Power University
LYU Kai
SUN Peng
REN Lijun

Related Institution

College of Energy and Power Engineering, North China Electric Power University
Guodian Longshan Power Generation Co., Ltd
Xi’an TPRI Energy Conservation Technology Co., Ltd.
Huaneng Weihai Power Generation Liability Co., Ltd.
Xi'an Thermal Power Research Institute Co.,Ltd.
0