L Hongqi. APPLICATION OF RUN BACK FUNCTIONS ONTO 50MW HEAT-SUPPLYING UNITS[J]. Thermal power generation, 2006, (5): 53-54.
DOI:
L Hongqi. APPLICATION OF RUN BACK FUNCTIONS ONTO 50MW HEAT-SUPPLYING UNITS[J]. Thermal power generation, 2006, (5): 53-54. DOI: 10.19666/j.rlfd.2006.05.017.
APPLICATION OF RUN BACK FUNCTIONS ONTO 50MW HEAT-SUPPLYING UNITS
摘要
对50 MW热电联产机组DEH存在的问题进行了改进
即在DEH中增加Run Back功能和一次调频功能
增大变负荷率
改进后
应用效果较好。
Abstract
The problems existing in DEH of 50 MW cogeneration units have been improved.After improvement
CAUSE ANALYSIS OF BAD SPEEDREGULATING QUALITY DURING STARTUP OF GASSTEAM COMBINED CYCLE'S STEAM TURBINE UNDER DIFFERENT OPERATING CONDITIONS AND REMEDIAL MEASURES THEREOF
A new optimization method for flow characteristic curve of control valve in steam turbines
Day ahead production decision model of flexible combined heat and power enterprises under energy and down-regulation market
Research progress of thermal energy storage technology in solar thermal power generation and combined heat and power generation
Optimization calculation for sliding pressure of steam turbine with extraction for heating
Related Author
HU Song
CHANG Peng
JIA Qiangbang
CUI Laijian
ZHANG Na
ZHANG Mingli
SONG Kun
XU XIlin
Related Institution
Moon Bay Gas Turbine Power Plant
Xi'an Thermal Power Research Institute Co., Ltd
Institute of Economics and Technology of State Grid Liaoning Electric Power Co. Ltd., Shenyang 1100152
State Grid Liaoning Electric Power Co., Ltd. Economic and Technical Research Institute
School of Electrical Engineering, Dalian University of Technology