MENG Yingqi, LI Xujun, YANG Shoumin. FEATURES OF COMMISSION DEBUGGING FOR HOME-MADE SUPERCRITICAL UNITS AS WELL AS ANALYSIS AND TREATMENT OF MAIN PROBLEMS[J]. Thermal power generation, 2005, (12): 1-3.
DOI:
MENG Yingqi, LI Xujun, YANG Shoumin. FEATURES OF COMMISSION DEBUGGING FOR HOME-MADE SUPERCRITICAL UNITS AS WELL AS ANALYSIS AND TREATMENT OF MAIN PROBLEMS[J]. Thermal power generation, 2005, (12): 1-3. DOI: 10.19666/j.rlfd.2005.12.001.
FEATURES OF COMMISSION DEBUGGING FOR HOME-MADE SUPERCRITICAL UNITS AS WELL AS ANALYSIS AND TREATMENT OF MAIN PROBLEMS
摘要
介绍了华能沁北电厂国产化首期600MW超临界机组系统设计、性能及辅机配置
较系统地阐述了该型机组起动调试的特点
并对调试过程中出现的主要问题和处理过程进行了分析讨论。
Abstract
The system design
performance
and auxiliary equipments allocation of first homemade 600 MW supercritical units in Huaneng Qinbei Power Plant have been presented
the features of commission debugging for said units being systematically expounded
and the main problems occurred in the process of debugging and their treatment course being analysed and discussed.
ESTABLISHMENT AND ANALYSIS OF DYNAMIC MATHEMATICAL MODEL FOR EMULATION SYSTEM OF SUPERCRITICAL 600 MW ONCE-THROUGH BOILER UNIT
ANALYSIS OF VIBRATION PROBLEM FOR HOME - MADE 600 MW SUPERCRITICAL TURBO - GENERATOR SET AND TREATMENT THEREOF
FEATURES OF SHAFTING SYSTEM FOR THE FIRST SUPERCRITICAL 600MW TURBO-GENERATOR SET MANUFACTURED BY BAPE CORPORATION,AS WELL AS VIBRATION ANALYSIS AND DISPOSAL THEREOF
FEED-WATER REGULATION OF SUPERCRITICAL BOILERS
PROPERTY ANALYSIS OF W-SHAPED FLAME BOILER FOR SUPERCRITICAL 600 MW UNIT