STRUCTURE AND BEHAVIOUR OF MAIN STEAM PIPELINE MADE FROM 12% Cr STEEL (F11) AFTER LONG-TERM OPERATION
Various mechanical behaviour tests and microscopic observation analysis for main steam pipeline made from material of F11 steel on unit No.1 in Yaomeng Power Generation Co Ltd after 100000 h operation have been carried out. It is considered after analysis that the structural aging and the behaviour embriflement of said material had occurred after 100000 h operation
but a certain residual life is still existing. The results have reference significance in technical study and applicable value in practical engineering for developing
utilizing and supervising main steam pipelines made from 12% Cr steel.