Construction risk assessment of shield crossing existing
bridge based on C-V-T model
As urban rail transit construction increases year by year
conflicts between new tunnels and existed bridges become increasingly obvious. Aiming at the risk assessment problem of shield tunnel crossing the existing bridge construction
and based on the system idea
we introduce the C-V-T model to classify the engineering risk into consequence severity
which is called C; the vulnerability of the existing bridge system
which is called V; and the threat of the new tunnel system
which is referred to as T
so as to construct a three-system risk assessment process of disaster-causing
disaster-bearing and post-disaster. By introducing the two-factor catastrophe theory to establish a three-level index system
we obtain the catastrophe progression of the existing bridge to express its vulnerability. In order to improve the accuracy of T-value
we use the interaction matrix to measure the cross influence between the indicators of the new tunnel
and then give the indicator-system weight method. Finally
introducing the complex mapping relationship and transformation situation between the quantitative indicators and qualitative concepts to express multi-dimensional cloud and forward generator optimization algorithm objectively. Additionally
we clarify the consequence severity grading criteria
by which defining the direct economic loss
the surrounding environmental loss and human casualty
give the coupling method of the three system risk assessment results
and thus build a comprehensive assessment model for the construction risk of shield crossing existing bridges. We apply the proposed model to the risk assessment of Yixin Bridge Crossing Project of Kunming Metro Line 5
which shows that the evaluation results match with the actual situation of the project. The construction monitoring data also verifies the rationality