LIU Wei-zheng, DAI Xiao-ya, SUN Kang, et al. Calculation method of longitudinal deformation of metro shield tunnel overpassing existing line at short distance[J]. 2022, 43(3): 831-842.
DOI:
LIU Wei-zheng, DAI Xiao-ya, SUN Kang, et al. Calculation method of longitudinal deformation of metro shield tunnel overpassing existing line at short distance[J]. 2022, 43(3): 831-842.DOI: 10.16285/j.rsm.2021.0864.
Calculation method of longitudinal deformation of metro shield tunnel overpassing existing line at short distance
In view of the uneven deformation of the operating subway line caused by the short-distance upward crossing construction of the new subway shield tunnel
the shield segments of the existing line are regarded as a series of short elastic beams connected by the tension spring
compression spring
and shear spring on the Pasternak foundation. The rotation effect and shear effect between segments and the interaction between segments and soil are considered
and a method is developed for calculating the additional stress caused by the construction of new shield tunnel based on Mindlin theory
and the longitudinal deformation of the existing tunnel based on the principle of minimum potential energy. The applicability of this method is verified by comparing with the measured data and the existing methods. According to the engineering example
the proposed method is used to analyze the influence of the segment connection
soil mechanical parameters
relative position parameters between the new line and the existing line and the reinforcement effect on the longitudinal deformation of metro shield tunnel. The results show that the friction force f and grouting pressure p heavily affect the deformation of the existing tunnel when a new tunnel is constructed to the upper crossing part
and that the longitudinal deformation is mainly affected by the unloading additional stress F when the new tunnel passes through the existing tunnel. With increasing shear stiffness ks and tensile stiffness kT
the uplift deformation of the existing line decreases
and ks has a relatively greater influence. The tunnel deformation can be controlled by enhancing the values of ks and kT
and the ring support reinforcement measures can effectively control the longitudinal deformation of the existing line
and the ring spacing of 1.5 m and 3?5 rings around the intersection point can achieve good results.
Longitudinal deformation of existing tunnel due to underlying shield tunneling
Discussion on failure mechanism of retrogressive landslide and its reinforcement measures: taking a certain expressway retrogressive landslide for example
Study of gully bed erosion depth of viscous debris flow
Review of calculation methods of earth berm before retaining structure and a new simplified analytical method
Calculation method for ultimate bearing capacity of inflatable anchor
Related Author
HUANG Hong-wei
ZONG Xiang
ZHANG Dong-mei
ZHANG Si-yuan
ZHOU Ying-bo
XU Zhi-zhong
SHEN Bo
REN Wei-zhongP
Related Institution
Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Tongji University
Department of Geotechnical Engineering, Tongji University
Highway Authority of Enshi Autonomous Prefecture
State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences