CHEN Nian, WANG Cheng-hu, GAO Gui-yun, et al. Characteristics of in-situ stress field in the powerhouse area on the right bank of Baihetan based on stress polygon and borehole breakout method[J]. 2021, 42(12): 3376-3384.
DOI:
CHEN Nian, WANG Cheng-hu, GAO Gui-yun, et al. Characteristics of in-situ stress field in the powerhouse area on the right bank of Baihetan based on stress polygon and borehole breakout method[J]. 2021, 42(12): 3376-3384.DOI: 10.16285/j.rsm.2021.0380.
Characteristics of in-situ stress field in the powerhouse area on the right bank of Baihetan based on stress polygon and borehole breakout method
The Baihetan hydropower plant is one of the most important backbone energy points of power transmission from west to east in China’s energy layout. In the initial stage of hydropower plant construction
some in-situ stress data were obtained by using conventional methods. However
with the continuous excavation of underground cavern
significant brittle failures caused by high stresses were observed in the surrounding rock. Therefore
the study on the stress field of surrounding rock mass is highly important for the long-term stability control of underground caverns. The borehole wall was scanned by the high-precision ultrasonic downhole television imaging system to obtain the logging image
and the widths of breakouts WBO was extracted by WellCAD software. The stress polygon based on Mohr-Coulomb criterion and Anderson theory and the breakout failure method based on Wiebols-Cook criterion were integrated and utilized to limit the estimation of stresses value
the characteristics of rock mass stress field in the project area were analyzed. The results show that the orientation of the maximum horizontal principal stresses in the engineering area was about N30.15°E
and the magnitudes of the major principal stresses were Sh=11.62±0.34 MPa (horizontal minimum principal stress)
SV=14.45±0.33 MPa (vertical principal stress)
SH=25.88±5.61 MPa (horizontal maximum principal stress) respectively. This stress state is favorable for the strike-slip faulting(Sh