Research on the diffusion mechanism and application of pulsate grouting in embankment and dam
Based on the characteristics of low frequency periodic pulse pressure
a new method was proposed for seepage control and reinforcement of a dam. A prototype test of a manmade homogeneous embankment demonstrated that the method
considering drilling disturbances and repetitive pulsating pressure on the permeability of strata
was feasible. The clay-cement slurry pulsation diffusion equation was determined using the multi-coupling software COMSOL to investigate the mechanism of fluctuati
ng pressure under the clay-cement slurry diffusion. Finally
this research was successfully applied to the Hebi section of the middle route water diversion channel along the grout curtain slope. The results showed that the 28-day strength of stone was greater than 2 MPa and the permeability coefficient was reduced to approximately 10
-5
cm/s
demonstrating that the clay-cement slurry pulsation control grouting technology can significantly improve the stratigraphic continuity. Observations were made on the slurry in the grouting hole near the soil and cement block
the adjacent grouting hole slurry vein staggered lap joint
and the overall performance of the impervious wall space of the three-dimensional structure. Based on a comprehensive analysis of the numerical simulation and the field test results
the dam grouting time fluctuation should remain between 1 800 s and 2 400 s
a reasonable grouting pressure pulsation should be between 0.2 MPa and 2 MPa
the pulse duration should be between 4 s and 8 s
and the pulse interval time should be adjusted to between 2 s and 6 s. These values ensure that the seepage and the reinforcement of the dam grouting remain in optimal engineering ranges. The channel slope continuity and integrity were improved
and significant improvement was noted for grout reinforcement sealing. The coefficient was reduced to 10
-5
cm/s
and the core sample remained as a whole with the length up to 40 cm.
Coupling mechanism of seepage and heat transfer in rock fracture based on physics-informed neural networks
Influence of construction gap on the force of steel lining in compressed air storage cavern
Stability and failure mode analysis of tunnel face in composite ground with upper sand and lower clay layers
Characterization method for the three-dimensional soil cutting failure surface based on damage energy dissipation
Pullout simulation on fully grouted rock bolts based on residual shear strength
Related Author
WANG Zhi-liang1
XIAO Zhi-huan1
SHEN Lin-fang1
LI Shao-Jun2
ZHANG Gui-min
SUN Wen-qing
ZHU Ze-fan
SU Yong-kang
Related Institution
Faculty of Civil Engineering and Mechanics, Kunming University of Science and Technology
State Key Laboratory of Geomechanics and Geotechnical Engineering Safety, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences
School of Mechanics and Civil Engineering, China University of Mining and Technology
State Key Laboratory of Intelligent Construction and Healthy Operation and Maintenance of Deep Underground Engineering, China University of Mining and Technology