Targeted research is performed on several problems about the application of the soil nailing wall combined with row piles in tunnel deep foundation pit support. Based on the theoretical and numerical analysis of engineering examples
the selection principle are proposed for the slope ratio i of soil nailing wall
the diameter-separation distance of the row pile as well as the relative stiffness between row pile and inner support while the inner support is applied. It is shown that 1) the smaller the value of i
the more stable the soil nailing wall
but the larger the moment and the displacement on the row pile are. The value of i should take a small value when the sliding stability of the soil nailing wall is fulfilled. 2) The larger the diameter and space between the piles
the smaller the horizontal displacement of the row pile
so that less concrete and steel rebar is required
resulting in a more cost-effective design
though the protection for the soil between piles will be more difficult. Hence
the diameter and the space between the pile should assume larger values when the engineering geological conditions is good and the water level is low
and vice versa. 3) Supporting effect of weak pile with strong support is better
but the construction interference for the surroundings is larger
while the cost of the strong pile (non-cantilever) with weak support is less. To achieve the purpose of safety and reliability and economical efficiency
it is necessary to consider engineering geological conditions
surrounding environment requirements
construction period
cost
and so on
in selecting the relative stiffness of the pile need.