Analysis and design aiming at control of upwarping deformation of existed tunnel under new tunnel’s excavation
The protection of two existed tunnels which are right under the Longpan tunnel’s excavation located in Nanjing Railway Station’s Square is presented. Due to the combining use of piles retaining and strips of excavation
the existed shield tunnel’s upwarping during the excavation is controlled successfully. The analysis and calculation of existed tunnel’s upwarping
the piles retaining’s design and the deformation’s supervision during the construction are also analyzed in detail. This excavation made a good example for the future similar engineering.