Based on the strategic deployment of the national coal power industry to implement energy conservation and emission reduction upgrades. For the units of Guangxi Investment Group Laibin Power Generation Co.
Ltd.
there are problems such as insufficient heating capacity and in-depth peak shaving flexibility
and high standard coal consumption rate for power supply. Therefore
the feasible technical solutions and treatment measures for heating optimization
flexibility transformation
energy saving and carbon reduction
and coal power upgrading and transformation of 300 MW units are obtained through the analysis and effect prediction of equipment system transformation such as unit heating pipelines. After these technical transformations are adopted
the heating capacity of the unit and the flexibility of deep peak regulation will be comprehensively improved
and the coal consumption for power supply will be reduced to 300 g/(kW·h). It could provide guidance for the flexible transformation of similar power plant units and the analysis and implementation of technical transformation to achieve the goal of power supply coal consumption of 300 g/(kW·h).