Yang Zhongjie, Wang Jiachen, Xu Wanchang, et al. Cause Analysis and Treatment of Grounding Transformer Protection Misoperation in a Photovoltaic Power Station[J]. Rural Electrification, 2026, (7): 70-75.
Yang Zhongjie, Wang Jiachen, Xu Wanchang, et al. Cause Analysis and Treatment of Grounding Transformer Protection Misoperation in a Photovoltaic Power Station[J]. Rural Electrification, 2026, (7): 70-75.DOI: 10.13882/j.cnki.ncdqh.2604F033.
Cause Analysis and Treatment of Grounding Transformer Protection Misoperation in a Photovoltaic Power Station
This paper investigates an incident at a photovoltaic power station in which misoperation of grounding transformer protection causes a complete outage of the 35 kV Section II busbar. Through accident investigation and short-circuit current analysis
it reveals the cause of the protection misoperation and the mechanism of setting-value coordination failure. To prevent misoperation of grounding transformer protection from happening again
the grounding transformer protection is systematically optimized in accordance with national standards for new energy grid-connected relay protection and staged protection technical requirements
from three aspects: setting configuration
time-delay graded coordination
and protection configuration integrity. Verification confirms that the optimized scheme satisfies both the time-delay grading requirement of ≥0.3 s and the timing coordination criterion
effectively preventing protection misoperation. This paper provides a technical reference for the safe and stable operation of photovoltaic power stations.