TAN Qiaofeng, WANG Yichen, WEN Xin, et al. Real-time Optimal Scheduling of Cascaded Hydropower Stations Under High-intensity Peak Shaving and Frequency Regulation[J]. 2026, 46(9): 3538-3550.
DOI:
TAN Qiaofeng, WANG Yichen, WEN Xin, et al. Real-time Optimal Scheduling of Cascaded Hydropower Stations Under High-intensity Peak Shaving and Frequency Regulation[J]. 2026, 46(9): 3538-3550.DOI: 10.13334/j.0258-8013.pcsee.242626.
Real-time Optimal Scheduling of Cascaded Hydropower Stations Under High-intensity Peak Shaving and Frequency Regulation
Under high-intensity peak shaving and frequency regulation
the hydropower station's output frequently fluctuates significantly
facing challenges such as water level fluctuations
unfavorable operating conditions for units
and frequent gate adjustments
greatly complicating the real-time optimization and scheduling of cascade power stations. This paper establishes a multi-unit coordinated precise control method for cascade hydropower plants involving "unit-gate" systems
considering the need for stable water levels
reduced gate adjustments
optimized operational conditions
and minimized water consumption. Models for gate optimization
precise water level control
and real-time load distribution are developed
exploring the coupling and nesting mechanisms across multiple models and scales. This approach is applied to the cascade hydropower stations situated in the middle reaches of the Dadu River. The results indicate a 44.22% reduction in the frequency of gate usage in cascade power plants. The number of units start-stop and vibration zone crossings has decreased by 54.29% and 55.87%
respectively. Furthermore
the water level fluctuations in three daily regulation plants has decreased by 47.86%
67.82%
and 75.76%
respectively. The water consumption rates have decreased by 0.03
0.03
and 0.01 m³/(kW·h)
respectively. Under high- intensity peak shaving and frequency regulation conditions
this method significantly enhances both the operational stability and power generation efficiency of the stations
thereby ensuring the safe operation of the new power system and the associated cascade hydropower stations.