Jiaqi CUI. Quality Management System and Maturity Evaluation of Overseas Flexible HVDC Transmission Project[J]. Power Generation Technology, 2020, 41(4): 361-368.
Jiaqi CUI. Quality Management System and Maturity Evaluation of Overseas Flexible HVDC Transmission Project[J]. Power Generation Technology, 2020, 41(4): 361-368. DOI: 10.12096/j.2096-4528.pgt.19015.
海外柔性直流输电工程项目的质量管理与国内的工程质量管理存在一定差异。在管理过程中,需要根据国际相关标准的项目质量管理思路,树立正确的质量管理理念。结合ISO 9001:2015、ISO 21500:2012和PMBOK质量管理体系标准,从知识管理、变更管理、资源管理、利益相关者管理、风险管理、沟通管理6个方面改进项目质量管理流程,提出适用于海外柔性直流输电工程项目的质量管理体系。最后,提出了海外柔性直流输电工程项目质量管理成熟度综合评价方法,对该体系成熟度进行了分析验证,为海外柔性直流输电工程项目质量管理工作提供借鉴。
There are certain differences between the quality management of overseas flexible HVDC transmission project and domestic engineering quality management. In the management process
it is necessary to establish a correct quality management concept based on the project quality management ideas of international relevant standards. Combining ISO 9001:2015
ISO 21500:2012 and PMBOK quality management system standards
the project quality management process was improved from six aspects of knowledge management
change management
resource management
stakeholder management
risk management and communication management
and a quality management system suitable for overseas flexible HVDC transmission project was put forward. Finally
the comprehensive evaluation method of quality management maturity of overseas flexible HVDC transmission project was put forward
and the maturity of the system was analyzed and verified
which provides reference for quality management of overseas flexible HVDC transmission project.
邢志宏, 温卫强.浅谈高压输电线路工程质量管理与控制[J].图书情报导刊, 2010, 20(27):209-211.
Xing Z H, Wen W Q.On the quality management and control of high-voltage transmission line engineering[J].Library and Information Guide, 2010, 20(27):209-211.
林鹏.高压输电线路工程质量管理研究[D].北京: 华北电力大学, 2014. http://cdmd.cnki.com.cn/Article/CDMD-10079-1014365746.htm .
Lin P.Research on quality management of high-voltage transmission lines[D].Beijing, China: North China Electric Power University, 2014.
许建林.全面质量管理理论与ISO 9000质量管理体系标准[J].山西建筑, 2004, 30(3):80-81.
Xu J L.Total quality management theory and ISO 9000 quality management system standards[J].Shanxi Architecture, 2004, 30(3):80-81.
汤广福, 贺之渊, 庞辉.柔性直流输电工程技术研究、应用及发展[J].电力系统自动化, 2013, 37(15):3-14.
Tang G F, He Z Y, Pang H.Research, application and development of flexible direct current transmission engineering technology[J].Power System Automation, 2013, 37(15):3-14.
邹丹, 艾欣, 王奥, 等.三端背靠背柔性直流输电的虚拟同步发电机控制策略及其在配电网中的应用[J].发电技术, 2018, 39(3):233-239.
Zou D, Ai X, Wang A, et al.Virtual synchronous generator control strategy of three-terminal back-to-back flexible DC transmission and its application in distribution network[J].Power Generation Technology, 2018, 39(3):233-239.
王云茂.厦门柔性直流输电工程调试安全质量管控综述[J].中国设备工程, 2017(2):172-173.
Wang Y M.Summary of the commissioning safety quality control of Xiamen flexible DC transmission project[J].China Equipment Engineering, 2017(2):172-173.
吴明哲, 陈武晖.VSC-HVDC稳定控制研究[J].发电技术, 2019, 40(1):28-39.
Wu M Z, Chen W H.Research on VSC-HVDC stability control[J].Power Generation Technology, 2019, 40(1):28-39.
Han C, Chen Y, Wu X Y, et al.Study on the safety and quality management innovation of power transmission and transformation projects in Jiangsu Province[J]. Applied Mechanics and Materials, 2015, 737(7):269-272.
Yu X Y, Liang L, Yu M, et al.Staged cost influence factors analysis on power transmission project[J]. Applied Mechanics and Materials, 2014, 590:5.
余晓钟.石油工程项目管理成熟度评价模型研究[J].当代石油石化, 2009, 17(4):28-32.
Yu X Z.Research on evaluation model of petroleum engineering project management maturity[J].Contemporary Petrochemicals, 2009, 17(4):28-32.
蒋洪强, 马向春, 杨玲玲.基于GIOWA算子的大型水利水电工程项目环境管理成熟度评价研究[J].长江流域资源与环境, 2010(S1):172-177.
Jiang H Q, Ma X C, Yang L L.Research on environmental management maturity evaluation of large-scale water conservancy and hydropower project based on GIOWA operator[J].Yangtze River Basin Resources and Environment, 2010(S1):172-177.
林向义, 刘晶, 魏景柱.钻井工程项目管理成熟度评价[J].工程管理学报, 2011, 25(5):548-552.
Lin X Y, Liu J, Wei J Z.Drilling project management maturity evaluation[J].Journal of Engineering Management, 2011, 25(5):548-552.
刘启波, 蒲继生.灰色聚类综合评价方法在住宅建筑方案选优中的应用[J].基建优化, 2002, 23(3):35-37.
Liu Q B, Pu J S.Application of grey clustering comprehensive evaluation method in the selection of residential building schemes[J].Infrastructure optimization, 2002, 23(3):35-37.
王金生.灰色聚类法在土壤污染综合评价中的应用[J].农业环境科学学报, 1991(4):27-30.
Wang J S.Application of grey clustering method in comprehensive evaluation of soil pollution[J].Journal of Agricultural Environmental Sciences, 1991(4):27-30.
孙伟诺.大型工程项目质量保证制度体系研究[D].长沙: 中南大学, 2010. http://cdmd.cnki.com.cn/Article/CDMD-10533-2010186232.htm .
Sun W N.Research on quality assurance system of large-scale engineering projects[D].Changsha, China: Central South University, 2010.
杨全义, 符志民.质量管理成熟度模型评价[J].项目管理技术, 2011, 9(3):34-38.
Yang Q Y, Fu Z M.Evaluation of quality management maturity model[J].Project Management Technology, 2011, 9(3):34-38.
0
Views
0
下载量
0
CSCD
Publicity Resources
Related Articles
Related Author
Related Institution
京公网安备11010802024621