Environmental licensing of new transmission systems in brazil: framing criteria by environmental agency
Solving Crisis|更新时间:2026-07-15
|
Environmental licensing of new transmission systems in brazil: framing criteria by environmental agency
Global Energy InterconnectionVol. 3, Issue 5, Pages: 423-429(2020)
作者机构:
1. Agriculture and Environmental Engineering Department-Engineering School. Universidade Federal Fluminense. R. Passo da Pátria, 156-237-São Domingos, Niterói,RJ,Brazil,24210-240
2. Water Resources and Environmental Engineering Department-Engineering School. Universidade Federal Fluminense. R. Passo da Pátria, 156-209 - São Domingos, Niterói,RJ,Brazil,24210-240
3. Electric Sector Study Group - Federal University of Rio de Janeiro (UFRJ)-Institute of Economics Red Beach Campus Av. Pasteur, 250 - Urca, Rio de Janeiro,RJ,Brazil,22290-240
Ricardo Abranches Felix Cardoso Junior, Alessandra Schwertner Hoffmann, Lillian Monteath, et al. Environmental licensing of new transmission systems in brazil: framing criteria by environmental agency[J]. Global Energy Interconnection, 2020, 3(5): 423-429.
DOI:
Ricardo Abranches Felix Cardoso Junior, Alessandra Schwertner Hoffmann, Lillian Monteath, et al. Environmental licensing of new transmission systems in brazil: framing criteria by environmental agency[J]. Global Energy Interconnection, 2020, 3(5): 423-429.DOI: 10.1016/j.gloei.2020.11.002.
Environmental licensing of new transmission systems in brazil: framing criteria by environmental agency
The growing demand for electricity in large Brazilian cities and the distance to the region with the largest energy production have encouraged the construction of transmission lines thousands of kilometers long
crossing several states of the federation. Therefore
the heterogeneity of requirements in federal
state and district environmental laws tend to lead to uncertainty for the investor regarding procedures and investments necessary for the completion of the project
as well as the time that the requirements will take to be fulfilled. In the present study
we identify and compare the criteria used by the various environmental licensing agencies for classifying transmission system projects in the different procedures (simplified and ordinary) of environmental licensing. It was possible to expose the differences and demonstrate some inconsistencies in the legislation of some Brazilian states. In particular
we note an absence of proportionality between the licensing requirements and the expected environmental impacts for projects on the physical
biological and social environments. Additionally
it was identified subjectivity in the requirement for social participation through public hearings
demanded by the legislation for the projects classified in the ordinary procedure.
Transmission line fault-cause identification method for large-scale new energy grid connection scenarios
Empowering the grid: A comprehensive review of vehicle-to-grid technology, digital twins, and intelligent energy systems
Optimal scheduling of renewable energy system based on probabilistic power balance under dynamic frequency security
Advancing electric vehicle ecosystems: a survey of generative artificial intelligence and distributed machine learning applications
The impact of increased renewable energy penetration and reduced inertia on the frequency nadir in a multi-area interconnected network based on the peninsula Malaysia national grid
Related Author
Hanqing Liang
Xiaonan Han
Haoyang Yu
Fan Li
Zhongjian Liu
Kexin Zhang
Related Institution
State Power Economic and Technological Research Institute Co, Ltd