PAN Ren-jun, DENG Zheng-wen, XIE Yu-hui, et al. Discussion on protection scheme for 110kV ring network during pilot protection shutdown[J]. 2008, (2): 49-50+59.
PAN Ren-jun, DENG Zheng-wen, XIE Yu-hui, et al. Discussion on protection scheme for 110kV ring network during pilot protection shutdown[J]. 2008, (2): 49-50+59.DOI:
Discussion on protection scheme for 110kV ring network during pilot protection shutdown
摘要
为提高对永州市的供电可靠性
在白竹亭变装设了110 kV BZT装置。由于该装置对运行方式的适应性不强
采用了城区110 kV环网结线加以改善
110 kV线路保护为单套配置并按远后备方案整定
但环网线路后备保护必然存在失配点
为此采用了线路纵联保护
而其中一回线路纵联保护停用时尚无完善的保护方案
这也是地区局所面临的共性问题
因此提出完善的保护方案具有普遍意义。
Abstract
To improve power supply reliability
a 110kV BZT was installed in Baizhuting substation.Because of its weak adaptability
110kV ring network topology in urban areas was adopted.110kV line protection was configured with single remote backup setting
which means mismatch points in ring network backup protection is inevitable
so pilot protection was adopted.However
there was no perfect protection scheme for one line pilot protection shutdown.A improving protection scheme was presented in the article.