REN Hua-gang1, NI Yu-gui2. Analysis on step and touch potential difference in the breakdown of power traction transmission lines[J]. 2011, 31(3): 25-28+52.
REN Hua-gang1, NI Yu-gui2. Analysis on step and touch potential difference in the breakdown of power traction transmission lines[J]. 2011, 31(3): 25-28+52.DOI:
Analysis on step and touch potential difference in the breakdown of power traction transmission lines
When the breakdown of substation frame or tower in transmission lines occurs in single-phase or interphase short circuit and grounding
grounding potential will rise
then possible step and touch potential will endanger personal safety.According to the measure and analysis of step and touch potential of 4th iron tower for 110kV Xinqian transmission line
corresponding countermeasure is presented and probable grouding risk is appraised in the paper.