Exploration and Practice of Main Steam and Reheated Steam Temperature Optimization Method for a Dual Circle Tangential Firing Boiler of a 1 000 MW Unit
|更新时间:2025-11-18
|
Exploration and Practice of Main Steam and Reheated Steam Temperature Optimization Method for a Dual Circle Tangential Firing Boiler of a 1 000 MW Unit
JIANG Sennian, YU Xiaowei, LIU Shuai, et al. Exploration and Practice of Main Steam and Reheated Steam Temperature Optimization Method for a Dual Circle Tangential Firing Boiler of a 1 000 MW Unit[J]. 2019, 39(4): 49-53.
JIANG Sennian, YU Xiaowei, LIU Shuai, et al. Exploration and Practice of Main Steam and Reheated Steam Temperature Optimization Method for a Dual Circle Tangential Firing Boiler of a 1 000 MW Unit[J]. 2019, 39(4): 49-53.DOI:
Exploration and Practice of Main Steam and Reheated Steam Temperature Optimization Method for a Dual Circle Tangential Firing Boiler of a 1 000 MW Unit
摘要
针对某1 000 MW机组双切圆锅炉启动调试期间出现的一系列问题
进行原因分析研究
提出了解决方法及优化思路。通过实际检验
问题得到解决
各项参数达到设计值
为同类型机组的运行调整提供强有力的借鉴。
Abstract
According to a series of problems that occurred during the start-up and commissioning of a 1000 MW dual circle tangential firing boiler
the causes are analyzed and the solution and the optimal thinking are put forward. Through the actual test
the problem is solved
and each parameter reaches the design value
which provides powerful reference for the operation adjustment of the same type of unit.