Method Difference of Putting the 800 kV Converter Transformer into Position between Electric Chain Hoist and Winch
|更新时间:2025-11-18
|
Method Difference of Putting the 800 kV Converter Transformer into Position between Electric Chain Hoist and Winch
Vol. 41, Issue 4, Pages: 65-69(2021)
作者机构:
国网湖南省电力有限公司建设分公司(咨询公司)
作者简介:
基金信息:
DOI:
CLC:TM40;TM721.1
Published:2021
稿件说明:
移动端阅览
赵子墨, 王东, 贺磊, et al. Method Difference of Putting the 800 kV Converter Transformer into Position between Electric Chain Hoist and Winch[J]. 2021, 41(4): 65-69.
DOI:
赵子墨, 王东, 贺磊, et al. Method Difference of Putting the 800 kV Converter Transformer into Position between Electric Chain Hoist and Winch[J]. 2021, 41(4): 65-69.DOI:
Method Difference of Putting the 800 kV Converter Transformer into Position between Electric Chain Hoist and Winch
摘要
介绍环链电动葫芦和卷扬机牵引800 kV换流变压器就位方法
对其受力情况进行了计算。结合雅中换流站工程实际
对两种方法的牵引时长、工器具配置、人工投入等方面开展了对比分析
对后续工程中换流变压器牵引就位的方案设计具有借鉴意义。
Abstract
Two different traction methods of converter transformers are introduced
and the force during the towing process is calculated. Combined with the actual engineering of the Yazhong converter station
the traction time
tool configuration
and manual input of two methods have been compared and analyzed.The results can be used as reference for the design of converter transformer traction scheme in the following projects.