Influence of shield tunneling on working performance of large interchange's super-long piles
|更新时间:2026-06-25
|
Influence of shield tunneling on working performance of large interchange's super-long piles
Vol. 35, Issue 10, (2014)
作者机构:
1. 天津大学 滨海土木工程结构与安全教育部重点实验室,天津,300072
2. 郑州航空工业管理学院 土木工程学院,郑州,450015
3. 天津市地下铁道集团有限公司,天津,300000
作者简介:
基金信息:
DOI:
CLC:U455.43
Online First:27 October 2014,
Published:2014
稿件说明:
移动端阅览
GUO Yi-bin, ZHANG Li-ming, ZHENG Gang, et al. Influence of shield tunneling on working performance of large interchange's super-long piles[J]. 2014, 35(10).
DOI:
GUO Yi-bin, ZHANG Li-ming, ZHENG Gang, et al. Influence of shield tunneling on working performance of large interchange's super-long piles[J]. 2014, 35(10).DOI:
Influence of shield tunneling on working performance of large interchange's super-long piles
Shield tunneling passing through adjacent large interchange's super-long piles has negative effect on super-long piles and bridge structures. Numerical analysis is conducted to simulate the process of the shield tunneling passing through the adjacent super-long piles. The bearing performance
deformations and forces of super-long piles caused by the shield tunneling with different depths are investigated. Some conclusions are drawn as follows. Large deformations and forces may occur in piles due to nearby tunneling. The various tunneling locations have different influences on the behaviors of piles. The most unfavorable position for lateral displacement is the upper part of pile; the most unfavorable position for longitudinal displacement is the middle part of pile; the most unfavorable position for vertical displacement is the tip of pile; the most unfavorable position for additional axial force is the lower part of pile
when other conditions are the same. The shaft resistances appear ‘S-shaped’ distribution near the tunnel axis; meanwhile
the maximum axial forces of the piles are also located at the tunnel axis. Lateral and longitudinal deformations of piles that extend to bridge decks are considerable. Horizontal deformations of piles top should be strictly controlled while tunneling passing through adjacent interchange's super-long piles.