Prediction of soil settlement induced by double-line shield tunnel based on Peck formula
|更新时间:2026-06-25
|
Prediction of soil settlement induced by double-line shield tunnel based on Peck formula
Vol. 35, Issue 8, (2014)
作者机构:
浙江大学城市学院 土木工程系,杭州,310015
作者简介:
基金信息:
DOI:
CLC:TU44
Online First:14 August 2014,
Published:2014
稿件说明:
移动端阅览
CHEN Chun-lai, ZHAO Cheng-li, WEI Gang, et al. Prediction of soil settlement induced by double-line shield tunnel based on Peck formula[J]. 2014, 35(8).
DOI:
CHEN Chun-lai, ZHAO Cheng-li, WEI Gang, et al. Prediction of soil settlement induced by double-line shield tunnel based on Peck formula[J]. 2014, 35(8).DOI:
Prediction of soil settlement induced by double-line shield tunnel based on Peck formula
the calculation approaching to study the three-dimension soil settlement caused by ground loss during double-line parallel shield tunnel (DLPST) construction is proposed. Considering the influence of first tunnel construction on second tunnel and different excavation face positions of two tunnels
modified three-dimensional Peck formula is established. It was used to calculate soil settlement caused by both the first and the second shield tunnel construction and combined the results
then the total soil settlement induced by DLPST is obtained. It is indicated that this method forecast value almost satisfied the measured value. With two tunnels excavation facing before and after distance of approximation
the maximum soil settlement volume will gradually increase. With the depth of z increasing
the settlement slightly increases and the settlement slot width slightly reduces. When the two tunnel axis level distance (L) is small
the soil settlement volume will be larger
and it is accord with normal distribution. The maximum soil settlement volume will gradually reduce and the settlement curve shape will slowly change by V type into W type as the increase of L.