Feasibility research of high bench blasting belongs to multiple factors and complex system project. In view of the feasibility research status of high bench blasting
a method of feasibility of high bench blasting considering blasting mechanism is put forward. Through comparing with difficult burst positions ( bench top and bottom ) stress field variation trend of the existing ordinary bench and high bench blasting process
it is found that the use of high bench blasting can obtain the existing bench blasting equivalent or better blasting results. From the blasting mechanism analysis
it is shown that the high bench blasting technology in the Barun ore is feasible. The numerical analysis results show that the best detonation mode of high bench blasting is all grain simultaneous blasting; the better ones are intermediate and ends of the detonation initiation; the unsuitable way is the hole bottom detonation.
Calculation method of sliding surface stress based on segmented sliding surface stress measurement system
Relationship between particle micro and macro mechanical parameters of parallel-bond model
Dynamic point safety factor analysis method of seismic stability of geosynthetics reinforced soil slope
Analysis of effect of anchor on deformation and force of double-row piles
Numerical analysis and test verification of penetration resistance for bucket foundation installation considering effect of soil squeezing
Related Author
CHEN Huai-lin
YANG Tao
RAO Yun-kang
ZHANG Zhe
WU Hong-gang
XIE Jiang-wei
TENG Han-qing
ABI ERDI
Related Institution
State Key Laboratory of Intelligent Construction and Maintenance for Geotechnical and Tunnel Engineering under Extreme Environments, Southwest Jiaotong University
China Northwest Research Institute Co., Ltd., of CREC
China Railway Academy Co., Ltd.
School of River & Ocean Engineering, Chongqing Jiaotong University
State Key Laboratory of Geomechanics and Geotechnical Engineering, Institute of Rock and Soil Mechanics, Chinese Academy of Sciences